Which of the following is the MOST likely cause of poor risk management?
A Inadequate risk response planning
B Poor risk monitoring and control
C Lack of a prioritized list of risks
D Lack of detail in the project scope statement
C
Risk management cannot proceed without a prioritized list of risks.
Can someone clarify this? Why prioritized list of risks? Why not Inadequate risk response planning?
(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)
2008年11月28日 星期五
訂閱:
張貼留言 (Atom)
1 則留言:
I'm sure. Just for discussion. I think you don't execute qualitative analysis if you lack of a prioritized list of risks. So you may not understand the impact of risk of your project. It causes bigger problems than that you do inadequate risk response planning.