What is the MOST likely cause of poor risk management?

值得思考的題問……
我跟 william 同學有相同的問題……why?

Which of the following is the MOST likely cause of poor risk management?
A Inadequate risk response planning
B Poor risk monitoring and control
C Lack of a prioritized list of risks
D Lack of detail in the project scope statement



C
Risk management cannot proceed without a prioritized list of risks.

Can someone clarify this? Why prioritized list of risks? Why not Inadequate risk response planning?



(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

1 則留言:

Michael 提到...

I'm sure. Just for discussion. I think you don't execute qualitative analysis if you lack of a prioritized list of risks. So you may not understand the impact of risk of your project. It causes bigger problems than that you do inadequate risk response planning.