Which parts of the risk management process do not generally use organizational process assets as an input?
A Risk identification and qualitative risk analysis
B Qualitative and quantitative risk analysis
C Quantitative risk analysis and risk response planning
D Risk response planning and risk monitoring and control .
ANS:D
Since risk response planning focuses on previously identified risks and risk monitoring and control measures project performance, they do not need to make use of organizational process assets.
Source: PMBOKR Guide