2008年12月1日 星期一

about the Organizational process assets

Which parts of the risk management process do not generally use organizational process assets as an input?

A Risk identification and qualitative risk analysis

B Qualitative and quantitative risk analysis

C Quantitative risk analysis and risk response planning

D Risk response planning and risk monitoring and control .


ANS:D

Since risk response planning focuses on previously identified risks and risk monitoring and control measures project performance, they do not need to make use of organizational process assets.

Source: PMBOKR Guide

通常在了解 ITTO 時,我不會特別花力氣思考在
Organizational process assets 以及 Eterprise Environmental Factors
這兩個 Input
只不過,這一題提醒了我,相關的東西還是思考一下
(謝謝 William 同學分享)


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)


沒有留言: