Where could we find the risk list?

在http://www.free-pm-exam-questions.com/
讀到一題,滿有意思的……
跟大家分享……

You have recently joined as the project manager of a project. One of the project documents available to you lists all the risks in a hierarchical fashion. What is this document called?
A. Influence diagram.
B. Risk breakdown structure.
C. Risk management plan.
D. Risk register.

答案是什麼?先想想看再看答案哦……
按下下面「(閱讀全文並檢視所有回應)」,
就可以看答案了……
^__^





這一題有點陷阱
答案是 B....
想想看,為什麼 C 跟 D 兩個答案不對?

Immanuel,
Duncan


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

2 則留言:

Michael 提到...

我的直覺是D,答案選B的原因是題目中提到Risk被階層式的展開對嗎?

杜奕鋒 提到...

yes , the key word is "hierarchical"....

Without this word...
I think both C and D are the right answer.....