2008年10月23日 星期四

crosswind manual test of cost charpter

測驗的重點好像怪怪的,好像有些新版已不再提


特別是第10題
10. The highway project is in the middle of Planning when the project manager presents a status reporting method to the team. The team members haven't heard of this method before. It's called earned value. To attain buy-in from the team, the project manager begins to expain what earned value status reporting can do for the project, explaining that it will measure which of the following?

(A) time and cost
(B) scope, time and cost
(C) scope and cost
(D) scope and time

answer is (B) (Why not (A), why earned value is related scope?)
crosswind explain AC shows cost, PV shows time, EV shows scope.
^^^^^^^^^^^^?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

1 則留言:

杜奕鋒 提到...

the total scope should equal to all the deliverable of the project .....and whenever we finish the deliverable in the WBS ...we get the value of the deliverable... we take that as the value we have earned (EV)......