2008年12月5日 星期五

about the Work Performance Infromation

The Work Performance Infromation is the key output of the Direct and Manage Project Execution Process... and will be the input of
1. ALL the Monitoring & Controlling Process Groups (deside Schedule Control Process)
2. Close Project Process. ( for final closure report)
and
3. Perform Quality Assurance Porcess. ( for the activities to improve process quality)

My question is ......


Why isn't the Work Performance Infromation also the input of Schedule Control Process?
Needn't we use Work Performance Infromation to Control our shedule ?
Shouldn't we compare the data from Work Performance Infromation with shedule baseline?


(P.S. 本文章發佈在 PMP交流討論網 ,歡迎大家參與討論)

……(閱讀全文並檢視所有回應)

2008年11月28日 星期五

Project Time Management 的題目

滿有意思的題目……willaim 同學分享的
(想想看題目的在問那一個 process 發生的事,答案應該就出來了)
What might historical records from previous projects used as an input to activity definition include?
A . Activities
B Resources
C Costs
D Schedule



ans:A
This question is worded strangely! Get used to it because you will have many instances where it will take you two minutes to figure out what the question is asking, let alone come up with the best answer.

Also refer to Section 6.1.1 Activity Definition: Inputs  

.2 Organizational Process Assets

Organizational process assets (Section 4.1.1.4) contain the existing formal and informal activity planning-related policies, procedures, and guidelines that are considered in developing the activity definitions. The lessons-learned knowledge base contains historical information regarding activities lists used by previous similar projects that can be considered when defining project schedule activities.


 